Blaiken Procurement

Meventus' consultants managed the procurement of 99 wind turbines and saved the project more than 60 million euros from 1st offer to final contract.

Situation and objective

  • Utility client with ambitious plans in wind energy and secured finance backing from own balance sheet
  • Determined to utilise the financial downturn for procurement of large number of wind turbines
  • Client with little experience in procurement of wind turbines and lack of market knowledge (2-3 MW)
  • Objective of the project was to procure 118 onshore wind turbines rapidly at the right cost and with lowest operational life cycle risk

Approach

  • Management of the whole procurement process
  • Five-step Approach to Procurement applied with detailed supplier market analysis and evaluation of technology along product life cycle
  • Definition of the client requirements incl. make or buy analysis along value-chain and technical and commercial requirements
  • Definition of RfQ, negotiation strategy, supplier nomination, negotiations, factory inspections
  • Meventus consultants led supplier negotiations/selection

Results & Benefits

  • Good transparency of the supplier market with strengths and weaknesses by key player & market
  • Simple RFQ with functional specifications: 16 suppliers invited, 13 offers received (low cost & high value; direct drive & geared; US, European & Asian)
  • Four selection gates with 30%+ secured price reductions for WTG and O&M before 2nd gate
  • Duration of the total 3-phase project: ~12 months
  • Total savings from 1st offer to final contract: mio€ 60+

Do you require assistance in your procurement process?